KFC Yum! Center’s 15th Anniversary Brings Major Roof Replacement and Launch of Long-Term Strategic Planning

 

Major Roof Replacement Underway

  • A $13.6 million capital investment is being made this fall.
  • Project includes full replacement of the original 250,000 sq. ft. roof.
  • Roof replacement began August 4, 2025, and is expected to be completed by December 2025.
  • The new roof will carry a 30-year warranty for long-term durability.
  • Work is strategically scheduled to avoid disruptions to events.
  • As the KFC Yum! Center celebrates its 15th anniversary this October, the roof replacement is part of a larger initiative to reimagine and further enhance the arena. 

 

Long-Term Strategic Planning & Enhancements

  • Over the next 15 years, $100 million+ in additional capital improvement projects are envisioned

Project Partners

  • Deer Park Roofing, a Louisville-based company, was selected through a competitive RFP process to lead the roof project.
  • ASM Global and the Louisville Arena Authority (LAA) are coordinating closely to manage construction and long-term planning.

 

Ongoing Arena Operations

  • The KFC Yum! Center remains fully operational during construction.
  • No disruptions expected for concerts, University of Louisville athletics, or other scheduled events.

 

Stay Informed

  • Bookmark this page for the latest information. Updates will be made as needed.
  • Follow us on Facebook and Instagram for real-time updates and behind-the-scenes progress.